TULSA, OK --- Work on three worn out bridges is ahead of schedule. The first phase of repairs to three bridges along I-244 is finished.
ODOT is offering big incentives for contractors to wrap up before the Thanksgiving travel season. Engineers say the work could be finished as early as October First.