Nearly six blocks of streets in the downtown Broken Arrow area will be resurfaced is expected to begin October 11. While the project involves temporary road closures, businesses in the area will remain open and customers will be able to find parking nearby, the city said.
Streets to be resurfaced during this project include:
The City of Broken Arrow said the city contractor will first begin work on Commercial Street, and each street is expected to take approximately two weeks to complete, weather permitting.
All work is scheduled to be completed around Thanksgiving, weather permitting.
The project costs $373,134 and is funded through the 2008 General Obligation Bond.