Losing Bidders On I-35W Bridge Project Won't Miss Out Entirely

ST. PAUL (AP) _ Next week, four teams bidding to replace the fallen Interstate 35W bridge in Minneapolis will learn which has the inside track on a project that could be worth a quarter-billion dollars.

Friday, September 14th 2007, 4:48 pm

By: News On 6


ST. PAUL (AP) _ Next week, four teams bidding to replace the fallen Interstate 35W bridge in Minneapolis will learn which has the inside track on a project that could be worth a quarter-billion dollars.

But even the losers won't walk away empty-handed.

The Minnesota Department of Transportation is ready to pay $500,000 to each of the unsuccessful bidders, which a spokesman said is the largest stipend the agency has ever offered. If they accept the money _ they are free to turn it down _ the department gets the right to use any ideas losing teams submit.

Four teams met Friday's deadline to submit design proposals and they must attach a price tag to them by Tuesday. On Wednesday, the department will open the bids. The plan is to pick the winner by the end of the month. The project is expected to cost between $200 million and $250 million, and the builders can earn up to $27 million in incentives for speedy completion.

The four teams are: C.S. McCrossan Inc.; Ames Construction Inc. and Lunda Construction Co.; American Bridge Co. and Walsh Construction Co.; Flatiron Construction Corp. and Johnson Bros.

Three days after the Aug. 1 collapse that killed 13 people, Minnesota's transportation department issued its first call for contractors to compete to build the replacement. In that invitation, the agency offered a $300,000 stipend. About two weeks later the enticement was up to $400,000. Earlier this month, it rose to $500,000.

Department spokesman Kevin Gutknecht said the stipend increase reflects heightened expectations, including a requirement that the bridge be reinforced to accommodate a future light-rail line.

Stipends are a common feature of design-build transportation projects, an increasingly popular approach where a contractor is responsible for both the design and construction. The money is meant to make the projects more attractive to bid on because developing a proposal can be expensive.

Civil engineering professor Keith Molenaar of the University of Colorado at Boulder has studied the use of stipends and deems them valuable.

``You can't ask the industry to do all these thousands of hours of work and not be compensated,'' he said. ``I believe in the long term the cost of the stipend is far outweighed in the benefit of the innovation and time savings.''

Prior to this project, Gutknecht said the richest stipend Minnesota had awarded was $425,000 for teams competing to do the Highway 52 reconstruction in and around Rochester.

However, the I-35W bridge stipend won't even come close to big awards offered elsewhere, according to a report by transportation consultant Tom Warne, who is under contract in Minnesota to advise on the bridge project.

Bidders in Texas were paid a $1.3 million stipend to submit plans for a $1.3 billion state highway project, and Utah and Colorado both paid $950,000 stipends on $1 billion-plus freeway projects.
logo

Get The Daily Update!

Be among the first to get breaking news, weather, and general news updates from News on 6 delivered right to your inbox!

More Like This

September 14th, 2007

September 29th, 2024

September 17th, 2024

July 4th, 2024

Top Headlines

December 11th, 2024

December 11th, 2024

December 11th, 2024

December 11th, 2024