Tulsa city council to discuss penalty on South Yale project

The contractor widening South Yale near 71st Street in Tulsa might be docked almost a million dollars, or nothing at all. <br/><br/>The job was scheduled to be done last November. The contractor, Sherwood

Tuesday, April 11th 2006, 4:17 pm

By: News On 6


The contractor widening South Yale near 71st Street in Tulsa might be docked almost a million dollars, or nothing at all.

The job was scheduled to be done last November. The contractor, Sherwood Construction, claims problems with utilities in the area delayed the job.

Their contract with the city includes penalties for being late that's added up to $900,000.

The Tulsa city council will consider what to do about the penalty this Thursday.
logo

Get The Daily Update!

Be among the first to get breaking news, weather, and general news updates from News on 6 delivered right to your inbox!

More Like This

April 11th, 2006

March 14th, 2024

December 4th, 2023

September 25th, 2023

Top Headlines

March 29th, 2024

March 28th, 2024

March 28th, 2024

March 28th, 2024