Bridge Construction Closes 2 Downtown Tulsa IDL Ramps

There is&nbsp;a new&nbsp;orange barrel alert for&nbsp;drivers headed west on the Broken Arrow Expressway into downtown Tulsa. <br /><br /><a href="http://www.newson6.com/story/14642532/construction-on-first-phase-of-tulsas-double-deck-bridge-to-begin-this-weekend" target="_blank">First Phase Of Tulsa&#39;s Double Decker Bridge Project To Begin This Weekend</a>

Monday, May 16th 2011, 7:40 am

By: News On 6


NewsOn6.com

TULSA, Oklahoma -- There's a new orange barrel alert out for drivers headed west on the Broken Arrow Expressway into downtown Tulsa.

Construction on the first phase of a double-decker bridge over the Arkansas River is underway.

Friday night, the Oklahoma Department of Transportation closed two ramps, the westbound ramp to southbound I-244 over the bridge and the northbound ramp to Sand Springs on the IDL.

See map [right].

Both ramps will remain closed for the next two years and that means you will have to exit at 11th and Houston, unless you use the northbound leg of the IDL to go south on I-244 or to Sand Springs.

5/13/2011 Related Story: First Phase Of Tulsa's Double Decker Bridge Project To Begin This Weekend

The new I-244 bridge over the Arkansas River is what engineers describe as "multi-modal" - carrying all kinds of traffic, with a double decker design.

Cars will go on top and eventually passenger rail will go underneath.

Within the next month, all westbound traffic on I-244 will cross over before the bridge and the eastbound bridge will be taking both east and westbound traffic, so the westbound bridge can be demolished.

Read an Oklahoma Department of Transportation project overview.

logo

Get The Daily Update!

Be among the first to get breaking news, weather, and general news updates from News on 6 delivered right to your inbox!

More Like This

May 16th, 2011

April 15th, 2024

April 12th, 2024

March 14th, 2024

Top Headlines

April 26th, 2024

April 26th, 2024

April 26th, 2024

April 26th, 2024