Poor weather forces brief closure of Alaska pipeline, Prudhoe Bay

ANCHORAGE, Alaska (AP) -- Both the nation's largest oil field and the trans-Alaska oil pipeline that transports its crude oil were shut down Tuesday after poor weather caused havoc at both ends of

Tuesday, October 10th 2006, 9:21 pm

By: News On 6


ANCHORAGE, Alaska (AP) -- Both the nation's largest oil field and the trans-Alaska oil pipeline that transports its crude oil were shut down Tuesday after poor weather caused havoc at both ends of the 800-mile pipeline.

BP PLC said high winds were to blame for a power outage that shut down Prudhoe Bay in northern Alaska. Production fell to about 35,000 barrels Tuesday; about 350,000 barrels were produced Monday.

Flooding near the southern terminus of the pipeline caused by heavy rain is suspected of knocking out fiber-optic communication lines along the pipeline, causing its temporary shutdown, said Mike Heatwole, spokesman for Alyeska Pipeline Service Co., the company
that operates the pipeline.

Operators lost communications to remote valves that can be closed in the event of a spill. Heatwole said company protocol calls for the pipeline shutdown when valves cannot be closed from long distance. The valves must be staffed by crews that can manually operate the valves, he said.

The pipeline was brought back online early Tuesday afternoon after those crews arrived by helicopter, Heatwole said. It was out of service for about 10 hours.

At Prudhoe Bay, BP spokesman Daren Beaudo said, layers of dust and dirt blown by high winds built up on high voltage insulators on power lines and the field, causing a short just before 3 a.m.

"The whole field came down," Beaudo said.

While winds had dropped to about 12 mph at Deadhorse near the time of the outage, peak gusts were clocked at 66 mph at midday Monday, said Tom Dang of the National Weather Service.

Beaudo said crews work Tuesday to wash insulators, restore power and ramp up production. He could not predict whether the work would take more than one day.

Communications are a critical component for operations of the trans-Alaska pipeline, which carries nearly 17 percent of the nation's domestic oil supply daily.

"We lost communication with five of our remote gate valves just north of Valdez at about 4 a.m. Alaska time," Heatwole said.

The remote valves are important when there is a pipeline leak. They are closed to limit the amount that might be spilled in the affected section.

Flooding and mudslides along the Richardson Highway, which parallels the pipeline and is the only roadway out of Valdez, disrupted vehicle traffic. The Alaska Department of Transportation closed a 65-mile stretch of the highway, starting near Valdez.

The Weather Service said 6.5 inches of rain fell Sunday and Monday at Valdez. Flooding in Keystone Canyon near Valdez hit three bridges hard and moved one five feet, said DOT spokeswoman Shannon McCarthy.

High water along other roads in Valdez was hampering Alyeska's ability to staff the Valdez Marine Terminal, where oil is loaded onto tankers. The terminal is across Port Valdez from the city and a road leading to it was affected by flooding.

Heatwole said there was no disruption in Valdez operations. Essential employees reported to work at the Valdez harbor and were transported across Port Valdez by boat. One tanker was loaded Tuesday from oil from one of the facility's 14 500,000-gallon tanks. Another tanker is en route to Valdez, he said.

The entire Prudhoe Bay oil field had produced more than 400,000 barrels a day -- or 8 percent of total U.S. output -- until leaks and the discovery of pipe corrosion led the company to begin shutting down the eastern half of the field Aug. 6.

The eastern side of the field was restarted late last month as the company began to clean out the eastern transit pipeline.

BP workers this week are continuing to scrape and clean Prudhoe's east side transit line with devices called maintenance pigs. The work follows intensive ultrasonic inspections and other sound wave tests.

Next, workers will put a smart pig that uses ultrasound through the line to check for thin spots. BP officials declined to say exactly when that would occur, only that they were working on a two-week maintenance effort that began Sept. 30.

BP has said it ultimately will replace 16 of 22 miles of transit lines. It expects to get replacement pipe by the end of the year, with construction beginning early next year.
logo

Get The Daily Update!

Be among the first to get breaking news, weather, and general news updates from News on 6 delivered right to your inbox!

More Like This

October 10th, 2006

April 15th, 2024

April 12th, 2024

March 14th, 2024

Top Headlines

April 26th, 2024

April 26th, 2024

April 26th, 2024

April 26th, 2024