TULSA COUNTY -- The Oklahoma Department of Transportation begins its first stimulus project in Northeast Oklahoma.
Crews shut down part of State Highway 151 to replace two bridges that go over the highway near Keystone Dam.
Both bridges are structurally deficient.
Work is expected to take about six months and costs a little more than $7 million.