Sand Springs Street Overlays Set For Early May Start

The City of Sand Springs will see another round of pavement overlays – weather permitting – beginning the week of May 2. The project includes 21 streets and about six miles of roadway.

Friday, April 29th 2011, 4:56 pm

By: News On 6


NewsOn6.com

SAND SPRINGS, Oklahoma -- The City of Sand Springs will see another round of pavement overlays – weather permitting – beginning the week of May 2. The project includes 21 streets and about six miles of roadway.

Crews are planning to start on north side streets then move on to the remaining local streets. Curbed streets will be milled prior to the overlays so the pavement edge and gutters match. The milling will be scheduled during the project to minimize inconveniences to drivers and residents, according to T.J. Davis of Sand Springs Public Works.

Some of the streets will also be modified with ramps to provide handicapped access. The work will be done by Tulsa County road crews.

  • Renaissance Drive, Adams Rd. to Old North Rd. (overlay only).
  • Birch Avenue, 10th St. to Renaissance Dr. (overlay, HC ramp).
  • Cedar Avenue, 10th St. to 11th St. (overlay only).
  • Douglas Avenue, 10th St. to 11th St. (overlay only).
  • 11th Street, Birch Ave. to Elder Ct. (overlay only).
  • Woodland Drive, 10th St. to 10th Pl. (overlay only).
  • 10th Place, Woodland Dr. to Lake Dr. (overlay only).
  • Lake Drive, 10th Pl. to 10th St. (overlay only)
  • 11th Street, west of Adams Rd. (overlay only).
  • 11th Place, west of Adams Rd. (overlay only).
  • Pin Oak Court, south of 12th St. (milling, overlay).
  • 12th Street, McKinley Ave. to Adams Rd. (overlay, striping).
  • 26th Street, Bermuda Ave. to Maple Ave. (milling, overlay, HC ramps).
  • 27th Street, Bermuda Ave. to Maple Ave. (milling, overlay, HC ramps).
  • 27th Court, east of Bermuda Ave. (milling, overlay, HC ramp).
  • 28th Court, east of Bermuda Ave. (milling, overlay, HC ramp).
  • Nassau Avenue, 27th St. to 29th St. (milling, overlay, HC ramps).
  • Bahama Avenue, 27th St. to 29th St. (milling, overlay, HC ramps).
  • 129th West Avenue, 56th St. to 41st St. (overlay and striping).
  • 74th West Court, Rolling Oaks Dr. to 71st W. Ave. (overlay only).
  • 71st West Avenue, 74th W. Ct. to Rolling Oaks Dr. (overlay only).
logo

Get The Daily Update!

Be among the first to get breaking news, weather, and general news updates from News on 6 delivered right to your inbox!

More Like This

April 29th, 2011

April 15th, 2024

April 12th, 2024

March 14th, 2024

Top Headlines

April 19th, 2024

April 19th, 2024

April 19th, 2024

April 19th, 2024